October 23, 2009
|
Schedule Update Wire installation is continuing at locations in Penn Hills. A helicopter will be installing rope for wire pulling on Oct 28.
|
|
August 7, 2009
|
Schedule Update Helicopter will pull in rope as preparation for wire stringing near the Hospital. Crews will continue to set poles.
|
|
July 19, 2009
|
Schedule Update Setting poles in Penn Hills. Foundation work in Penn Hills.
|
|
July 1, 2009
|
Schedule Update Contractor digging foundations on McCutcheon Lane and Wilson Drive in Penn Hills Township and Sargent will be setting poles near the Vets hospital in the City of Pittsburgh.
|
|
June 19, 2009
|
Schedule Update Installing foundations in Penn Hills Township. Pole installation near the Vets Hospital.
|
|
June 11, 2009
|
Schedule Update Update to week of June 7.
|
|
June 8, 2009
|
Schedule Update Glenfield Drive in Penn Hills will be closed June 9.
|
|
June 4, 2009
|
Schedule Update Week of June 7 Drilling for poles #863 through #845 in Penn Hills.
|
|
May 29, 2009
|
Schedule Update Week of June 1 Drilling for poles #858 thru #862 in the east end of the City of Pittsburgh.
|
|
May 24, 2009
|
Schedule Update Week of June May 24 Site preparation work on Selvin Drive and Suncrest Drive in Penn Hills Township.
|
|
March 2, 2009
|
Started the removal of the existing conductor and towers.
|
|
January 22, 2009
|
(docket # A-2008-2077194) PA PUC Letter of Notification Approved
|
|
December 8, 2008
|
Draft of web site issued
|
|
November 24, 2008
|
Filed Letter of Notification with the PA Public Utility Commission
|
|
September 29 & 30, 2008
|
Held Public Workshop at the Comfort Inn
|